CMMS Guide · MU-PMD-001

PM Master Data Creation Manual

Step-by-step workflow to create and sign off PM master data — equipment, task lists, PM plans and measuring points — for a new asset.

Purpose

This manual walks planners, reliability engineers and CMMS administrators through the exact sequence required to stand up PM master data for a new asset or a maintenance strategy change. It is the operational companion to the CMMS Technical Build Guide.

Scope

  • New equipment commissioning
  • Strategy changes on existing assets (interval, task, resource)
  • Post-RCM master data updates
  • Master data sign-off before go-live

Key Terms

TermMeaning
Master dataThe reference records the CMMS uses to generate transactions — FLOCs, equipment, task lists, PM plans, BOMs.
Measuring pointA counter or reading (hours, cycles, tonnes) that drives usage-based PM schedules.
StrategyThe set of intervals a PM plan chooses from (e.g. 250 h / 1000 h / 2000 h).
Sign-offA named, dated approval by the accountable role — Reliability Engineer for strategy, Planner for job plan, Maintenance Leader for release.

Sections

  1. 01

    Confirm the asset & FLOC

    Intent

    Anchor everything to the correct position before creating a single PM record.

    Actions
    • Confirm the equipment is loaded, released and linked to the correct FLOC.
    • Confirm criticality is set — this drives interval and task selection.
    • Confirm the Object Type — inherited task list references and characteristics come from here.
    What Good Looks Like
    • One PM plan per maintenance concept — never bundle unrelated intervals to save clicks.
    • Reuse task lists across plans; only create a new task list when the work genuinely differs.
    What Bad Looks Like
    • Creating equipment before the FLOC exists — later hierarchy shifts break everything downstream.
    • Copy-pasting task lists between assets instead of linking — a small change becomes a project.
  2. 02

    Establish measuring points

    Intent

    Set up the counters that will drive usage-based PMs.

    Actions
    • Create measuring points for each usage measure that will trigger a PM (running hours, cycles, throughput).
    • Configure automatic reads from control system tags where available.
    • Set the reading interval and validation rules (min/max delta).
    What Good Looks Like
    • Use characteristics to drive PM selection where the CMMS supports it — future-proof against fleet expansion.
    • Load measuring points before releasing usage-based plans; blank counters silently suppress work orders.
    What Bad Looks Like
    • Creating equipment before the FLOC exists — later hierarchy shifts break everything downstream.
    • Copy-pasting task lists between assets instead of linking — a small change becomes a project.
  3. 03

    Create or link the task list

    Intent

    Attach the executable work steps to a reusable, controlled task list.

    Actions
    • Search the task list library for a matching Object Type task list before creating a new one.
    • New task lists follow the Task List Naming Convention and Task List Numbering standards.
    • Populate steps with duration, craft, materials and safety references.
    • Reliability Engineer signs off the task list before it is used by a plan.
    What Good Looks Like
    • Reuse task lists across plans; only create a new task list when the work genuinely differs.
    • Load measuring points before releasing usage-based plans; blank counters silently suppress work orders.
    What Bad Looks Like
    • Copy-pasting task lists between assets instead of linking — a small change becomes a project.
    • Forgetting to release the plan — no work orders ever generate and nobody notices for a quarter.
  4. 04

    Build the PM plan

    Intent

    Schedule the task list at the right interval on the right cycle.

    Actions
    • Pick the plan type (single-cycle, multi-counter, strategy) that matches the maintenance concept.
    • Set the start date, offset and completion horizon.
    • Confirm the maintenance item points at the correct FLOC/equipment.
    • Release the plan and generate the first call so the schedule can pick it up.
    What Good Looks Like
    • One PM plan per maintenance concept — never bundle unrelated intervals to save clicks.
    • Reuse task lists across plans; only create a new task list when the work genuinely differs.
    • Load measuring points before releasing usage-based plans; blank counters silently suppress work orders.
    What Bad Looks Like
    • Copy-pasting task lists between assets instead of linking — a small change becomes a project.
    • Forgetting to release the plan — no work orders ever generate and nobody notices for a quarter.
  5. 05

    Sign-off & release

    Intent

    Close the loop with named approvals so the master data is defensible.

    Actions
    • Complete the PM Master Data Sign-Off Checklist.
    • Reliability Engineer approves strategy (interval, tasks, materials).
    • Planner approves execution content (durations, sequence, resources).
    • Maintenance Leader approves release into live scheduling.
    • Filed in the master data change register.
    What Good Looks Like
    • One PM plan per maintenance concept — never bundle unrelated intervals to save clicks.
    • Reuse task lists across plans; only create a new task list when the work genuinely differs.
    What Bad Looks Like
    • Skipping sign-off because 'it's urgent' — the record has no owner and drifts silently.
    • Forgetting to release the plan — no work orders ever generate and nobody notices for a quarter.

Best Practices

  • One PM plan per maintenance concept — never bundle unrelated intervals to save clicks.
  • Reuse task lists across plans; only create a new task list when the work genuinely differs.
  • Use characteristics to drive PM selection where the CMMS supports it — future-proof against fleet expansion.
  • Load measuring points before releasing usage-based plans; blank counters silently suppress work orders.

Common Pitfalls

  • Creating equipment before the FLOC exists — later hierarchy shifts break everything downstream.
  • Copy-pasting task lists between assets instead of linking — a small change becomes a project.
  • Skipping sign-off because 'it's urgent' — the record has no owner and drifts silently.
  • Forgetting to release the plan — no work orders ever generate and nobody notices for a quarter.