Purpose
The Schedule Work phase converts a planned backlog into a firm, achievable weekly schedule. Effective scheduling maximises wrench time, protects proactive work, and gives operations a predictable maintenance window. Poor scheduling burns planned work as reactive fire-fighting.
Scope
- Weekly routine scheduling, shutdown scheduling and long-term strategy scheduling
- Resource levelling, backlog management, schedule compliance measurement
- Coordination between maintenance, operations, engineering and contractors
RCM Foundation
RCM consequence categories drive scheduling priority. When condition monitoring detects a potential failure, the corrective intervention must be scheduled inside the remaining P-F interval — that is a hard constraint, not a target. A healthy schedule is proactive-dominant: reactive work over 20% is an RCM strategy failure, not a scheduling problem.
Process Steps
- 01
Review previous period
IntentLearn from what actually happened last week before drafting the next schedule — every schedule starts by closing the loop on the previous one.
Inputs- Last week's committed schedule and actual completions
- Break-in log and schedule-breaker Pareto
- Carry-over work orders and their reasons
Actions- Calculate schedule compliance (jobs completed as scheduled ÷ jobs scheduled)
- Categorise carry-overs: material, labour, priority change, scope growth, break-in
- Update the schedule-breaker Pareto with the week's data
- Identify systemic issues to feed back to Planning or Identify Work
PeopleScheduler accountable. Planning Leader and Maintenance Leader consulted. Operations Leader receives the number.
ProcessFixed 30-minute review at a set time each week. Standard categories for compliance loss.
TechnologyCMMS schedule-compliance report. Break-in and carry-over categorised on the work order itself, not in a spreadsheet.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: compliance calculated inconsistently week-to-week
- The opposite of: carry-overs relabelled as 'still in progress'
- The opposite of: review skipped when it matters most (busy weeks)
What Bad Looks Like- Compliance calculated inconsistently week-to-week — the trend is meaningless
- Carry-overs relabelled as 'still in progress' — the number lies
- Review skipped when it matters most (busy weeks) — patterns never learned
Outputs- Compliance number published to leadership
- Updated schedule-breaker Pareto
- Actions logged for upstream owners
- 02
Filter Ready-to-Schedule backlog
IntentOnly fully planned work orders — materials confirmed, permits ready, labour estimated — are candidates for the schedule.
Inputs- Backlog of work orders in status Ready-to-Schedule
- Materials, permit and tool readiness flags
- Priority and must-complete-by dates
Actions- Filter to work orders that pass every readiness check
- Return not-ready work orders to Planning with reason — do not schedule optimistically
- Sort candidates by priority and P-F deadline
- Flag work waiting on long-lead items or shutdown windows
PeopleScheduler accountable. Planner owns the fix on returned work. Storeperson confirms kitting.
ProcessReady-to-Schedule is a hard status with defined criteria — not a label the planner sets when they feel finished.
TechnologyCMMS readiness view combining material, permit, tool and labour flags on a single screen.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: half-ready work scheduled to fill capacity
- The opposite of: readiness flags gamed to hit planning KPIs
- The opposite of: long-lead work permanently pushed right
What Bad Looks Like- Half-ready work scheduled to fill capacity — becomes reactive on execution day
- Readiness flags gamed to hit planning KPIs — schedule compliance collapses instead
- Long-lead work permanently pushed right — never scheduled at all
Outputs- Clean candidate list for the scheduling draft
- Not-ready work orders returned to Planning
- 03
Draft the schedule
IntentAllocate candidate work to days and crews across the schedule horizon, balancing capacity, priority and operational reality.
Inputs- Ready-to-Schedule candidate list
- Crew availability by day (leave, training, absentee factor)
- Downday and outage calendar
Actions- Load-level to 80–85% of available hours — leave headroom for break-ins
- Sequence work by asset and location to minimise travel and set-up
- Cluster PMs where operationally sensible; separate them when capacity peaks
- Slot condition-based work inside its P-F deadline — non-negotiable
- Draft alongside the operations plan — no maintenance-only schedule
PeopleScheduler accountable. Maintenance Supervisor consulted on crew loading. Operations Leader consulted on downdays and access.
ProcessStandard capacity model documented. Absentee factor reviewed quarterly. Schedule horizon fixed (typically 1 week firm, 2–4 weeks planned).
TechnologyCMMS scheduling board with drag-and-drop by day and crew. Capacity vs. load visible in real time.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: 100% capacity loading
- The opposite of: draft built in isolation from operations
- The opposite of: pM peaks left unlevelled
What Bad Looks Like- 100% capacity loading — every break-in blows the schedule
- Draft built in isolation from operations — downdays discovered at the meeting
- PM peaks left unlevelled — a month of overload followed by a month of drift
Outputs- Draft weekly schedule with work orders assigned by day and crew
- 04
Scheduling meeting
IntentOperations, Maintenance and Planning agree the committed schedule in one short meeting — decisions only.
Inputs- Draft schedule
- Production plan and downday calendar
- Constraint list (crew, contractor, material, permit)
Actions- Walk the draft together, day by day
- Confirm operational access for each downday
- Adjust for contractor windows and permit constraints
- Sign off the committed schedule — named signatures, not implied assent
- Log any scope trades and the reason
PeopleStanding attendees: Operations Leader, Maintenance Leader, Planning Leader, Scheduler. Reliability Engineer as needed.
ProcessFixed 30–45 minute meeting at a set time each week. Standard agenda. Decisions only — problems parked for follow-up.
TechnologySchedule projected on the wall or shared on screen. Signatures captured digitally against the schedule record.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: meeting becomes a debate
- The opposite of: operations absent
- The opposite of: schedule signed but not shared
What Bad Looks Like- Meeting becomes a debate — no schedule committed, planners re-work overnight
- Operations absent — access discovered wrong on the day
- Schedule signed but not shared — supervisors run yesterday's plan
Outputs- Committed weekly schedule signed by Operations, Maintenance and Planning
- Meeting log of trades and reasons
- 05
Publish and freeze
IntentTurn the committed schedule into a firm plan that everyone runs to — the schedule is frozen for scope, capacity may flex.
Inputs- Committed schedule from the meeting
Actions- Publish to Maintenance, Operations, Stores and Contractors at a fixed time
- Freeze scope: no addition without a break-in approval
- Confirm materials, permits and tools staged for Day 1 by end of the day prior
- Communicate any late changes with a formal update — never a corridor conversation
PeopleScheduler accountable for publication. Supervisors accountable for Day-prior readiness. Planning Leader owns freeze discipline.
ProcessPublication time is fixed and predictable. Scope changes require a documented break-in approval by named authority.
TechnologyCMMS or scheduling tool with role-based views. Automatic notification to affected supervisors and contractors.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: schedule published but never frozen
- The opposite of: late changes by phone
- The opposite of: day-prior readiness not checked
What Bad Looks Like- Schedule published but never frozen — priorities change hourly, nothing lands
- Late changes by phone — some crews run the old schedule, some the new
- Day-prior readiness not checked — first-hour on Monday is a scramble
Outputs- Published committed schedule visible to every stakeholder
- Day-prior readiness checklist complete
- 06
Manage break-ins
IntentHandle genuine emergent work honestly — captured as its own category, approved by name, and measured as a leading indicator.
Inputs- Emergent safety, environmental or production-critical work
- Committed schedule and its headroom
Actions- Assess whether the work truly cannot wait — P1 or hard P2 only
- Route to a named approver (Maintenance Leader or delegate)
- Displace scheduled work by name — never 'we'll get to it' quietly
- Log the break-in with cause, approver and displaced work
- Feed the break-in Pareto — top three causes get upstream action
PeopleMaintenance Leader approves. Scheduler updates the schedule. Operations Leader informed of displacement.
ProcessBreak-in approval is a controlled workflow, not an informal ask. Break-in rate tracked and reported weekly.
TechnologyCMMS break-in workflow with mandatory cause code and approver signature.
What Good Looks Like- Every crew member can point to where this step lives in the CMMS — no shadow spreadsheets.
- The opposite of: break-ins disguised as planned work
- The opposite of: everyone can approve
- The opposite of: displaced work quietly dropped
What Bad Looks Like- Break-ins disguised as planned work — schedule compliance looks fine while chaos reigns
- Everyone can approve — the discipline collapses in a fortnight
- Displaced work quietly dropped — backlog grows in the shadows
Outputs- Approved break-in with named displaced work
- Break-in log updated for the week
Key Performance Indicators
| KPI | Why It Matters | How To Measure | World Class | Benchmark | Typical |
|---|---|---|---|---|---|
| Schedule compliance | Schedule compliance is the single strongest leading indicator of a proactive site — if the frozen schedule holds, wrench time, reliability and cost all follow. | Hours executed against the frozen weekly schedule ÷ hours scheduled at freeze. Break-ins do not count as compliant work. | ≥ 95% | ≥ 90% | 40–60% |
| % available labour scheduled | Unscheduled labour is invisible capacity — it gets burned on low-value reactive work and never shows up in the improvement plan. | Scheduled crew hours (including PMs, projects, training) ÷ total available crew hours after leave and shift losses. | ≥ 90% | ≥ 85% | 50–70% |
| Reactive work in the schedule | Every hour of reactive work displaces two hours of proactive work — a high reactive ratio is a self-perpetuating spiral. | Reactive/breakdown work-order hours executed ÷ total maintenance hours executed in the period. | < 10% | < 15% | 40–70% |
| Break-in rate | Break-ins destroy the schedule the moment it is published — they signal weak triage, weak criticality, or a real reliability problem hiding in plain sight. | Work orders added to the frozen schedule after freeze ÷ total work orders in the executed schedule. | < 5% | < 10% | 25–40% |
| Backlog (ready to schedule) | Backlog is the shock absorber of the schedule. Too little and the schedule starves; too much and the backlog rots and trust collapses. | Total planned hours in status ‘Ready to Schedule’ ÷ weekly crew capacity in hours. | 3–4 weeks | 2–4 weeks of capacity | 0–1 week or >12 weeks |
Best Practices
- Schedule work orders down to the operation, not just the header
- Publish the schedule at a fixed time each week — predictability is the point
- Load-level PMs across the month, quarter and year — don't cluster PM peaks
- Track schedule breakers formally and Pareto them — the top three cover 80% of noise
- Long-lead-time materials scheduled backwards from need date, with an ordering trigger
Common Pitfalls
- 100% capacity loading — no room for break-ins, everything slips
- Priority replaces the schedule — everything urgent means nothing is
- No agreed downday calendar — maintenance and operations argue every week
- Break-ins disguised as planned work — schedule compliance looks fine while chaos reigns